Allocation and contract regulations for construction work (VOB)
Part B: General contractual conditions for the execution of construction work
§ 1 Type and scope of the service
1 . The type and scope of the service to be performed is determined by the contract. The General Technical Contract Conditions for Construction Services also apply as part of the contract.
2. In the event of contradictions in the contract, the following apply one after the other:
a) the service description,
b) the special contractual conditions,
c) any additional contractual conditions,
d) any additional technical contractual conditions,
e) the General Technical Contract Conditions for Construction Services,
f) the general contractual conditions for the execution of construction work.
3. The client reserves the right to order changes to the construction design.
4. Non-agreed services that are required to carry out the contractual service,
The contractor must carry out the work at the request of the client, unless his company is not equipped to provide such services. Other services can only be transferred to the contractor with his consent.
§ 2 Remuneration
1 . The agreed prices cover all services that are part of the contractual service according to the service description, the special contractual conditions, the additional contractual conditions, the additional technical contractual conditions, the general technical contractual conditions for construction work and commercial customs.
2. The remuneration is calculated according to the contractual standard prices and the services actually carried out, unless another method of calculation (e.g. a lump sum, hourly wage rates, cost price) has been agreed.
3. (1) If the exported quantity of the service or partial service covered by a standard price does not differ by more than 10%. H. depends on the scope provided for in the contract, the contractual standard price applies.
(2) If the quantity estimate is exceeded by more than 10%, a new price must be agreed upon request, taking into account the additional or reduced costs.
(3) If the quantity is undercut by more than 10 percent, the unit price for the actual quantity of the service or partial service carried out must be increased upon request, unless the contractor receives compensation by increasing the quantities for other ordinal numbers (items) or in some other way . The increase in the unit price should essentially correspond to the additional amount resulting from the distribution of the construction site equipment and construction site overhead costs and the general business costs over the reduced quantity. The sales tax will be reimbursed according to the new price.
(4) If the service or partial service covered by a standard price is dependent on other services for which a lump sum has been agreed, an appropriate change in the lump sum can also be requested when the standard price is changed.
4. If the contractor's services stipulated in the contract are taken over by the client himself (e.g. delivery of construction, construction materials and supplies), then, unless otherwise agreed, Section 8 No. 1 Paragraph 2 applies accordingly.
5. If the basis of the price for a service provided for in the contract is changed due to a change in the construction design or other orders of the client, a new price must be agreed, taking into account the additional or reduced costs. The agreement should be made before execution.
6. (1) If a service not provided for in the contract is required, the contractor is entitled to special remuneration. However, he must notify the client of the claim before he begins to carry out the service.
(2) The remuneration is determined based on the basis for determining the price for the contractual service and the specific costs of the required service. If possible, it should be agreed upon before work begins.
7. (1) If a lump sum is agreed as compensation for the service, the compensation remains unchanged. However, if the service performed deviates so significantly from the contractually agreed service that sticking to the lump sum is unreasonable (§ 242 BGB), compensation must be granted upon request, taking into account the additional or reduced costs. The basis of price determination must be used to calculate the compensation. Numbers 4, 5 and 6 remain untouched.
(2) Unless otherwise agreed, paragraph 1 also applies to lump sums agreed for parts of the service; Number 3 paragraph 4 remains unaffected.
8. (1) Services that the contractor carries out without an order or with an unauthorized deviation from the order will not be reimbursed. Upon request, the contractor must remove them within a reasonable period of time; otherwise it may be at his expense. He is also liable for other damages that the client incurs as a result.
(2) However, the contractor is entitled to remuneration if the client subsequently recognizes such services. He is also entitled to remuneration if the services were necessary for the fulfillment of the contract, corresponded to the presumed wishes of the client and were reported to him immediately. If the contractor is entitled to remuneration, the calculation bases for changed or additional services in numbers 5 or 6 apply accordingly.
(3) The provisions of the BGB regarding management without an order (§§ 677 ff. BGB) remain unaffected.
9. (1) If the client requests drawings, calculations or other documents that the contractor is not required to provide according to the contract, in particular the technical contract conditions or commercial custom, he must pay for them.
(2) If he has technical calculations not made by the contractor checked by the contractor, he must bear the costs.
10. Hourly wage work will only be remunerated if it has been expressly agreed as such before it begins (§ 15).
§ 3 Implementation documents
1. The documents required for execution must be handed over to the contractor free of charge and in a timely manner.
2. Delineating the main axes of the structures, as well as the boundaries of the area made available to the contractor, and creating the necessary height control points in the immediate vicinity of the structures are the responsibility of the client.
3. The terrain surveys and stakeouts provided by the client and the other documents handed over for execution are decisive for the contractor. However, to the extent that this is part of the proper fulfillment of the contract, he must check them for any discrepancies and point out any discovered or suspected defects to the client.
4. Before work begins, the condition of the roads and land surface, the receiving water and receiving pipes, as well as the structures in the construction area must, if necessary, be recorded in a record, which must be acknowledged by the client and contractor.
5. Drawings, calculations, verifications of calculations or other documents that the contractor must obtain in accordance with the contract, in particular the technical contract conditions, or commercial customs or at the special request of the client (§ 2 No. 9) are the responsibility of the client Request to be submitted in a timely manner.
6. (1) The documents mentioned in number 5 may not be published, reproduced, changed or used for any purpose other than the agreed one without the permission of their author.
(2) The client has the right to use DV programs with the agreed performance features in an unchanged form on the specified devices. The client may make two copies for data backup purposes. These must contain all identifying features. Proof of the whereabouts of the copies must be provided upon request.
(3) The contractor remains entitled to use the documents and the computer programs without prejudice to the client's right of use.
§ 4 Execution
1 . (1) The client must ensure that general order is maintained on the construction site and regulate the interaction between the various contractors. He has the necessary ones public law approvals and permits, e.g. B. according to building law, road traffic law, water law and commercial law.
(2) The client has the right to monitor the execution of the service in accordance with the contract. For this purpose, he has access to the workplaces, workshops and storage rooms where the contractual service or parts of it are manufactured or the materials and components intended for this purpose are stored. Upon request, the working drawings or other execution documents as well as the results of quality tests must be presented to him for inspection and the necessary information must be provided if this does not reveal any business secrets. Information and documents designated as business secrets must be treated confidentially.
(3) The client is authorized to make orders that are necessary to carry out the service in accordance with the contract, while maintaining the management of the contractor (number 2). In principle, the orders are only to be given to the contractor or his representative appointed to manage the execution, unless there is imminent danger. The client must be informed who has been appointed as the contractor's representative to manage the execution.
(4) If the contractor considers the client's orders to be unjustified or inappropriate, he must express his concerns, but carry out the orders upon request, unless legal or official regulations conflict with this. If this causes unjustified difficulty, the client must bear the additional costs.
2. (1) The contractor must carry out the service under his own responsibility in accordance with the contract. In doing so, he must observe the recognized rules of technology and the legal and official regulations. It is his responsibility to direct the execution of his contractual performance and to ensure order at his workplace.
(2) He is solely responsible for fulfilling the legal, official and trade association obligations towards his employees. It is solely his job to make the agreements and measures that regulate his relationship with the employees.
3. If the contractor has concerns about the intended type of execution (also because of protection against the risk of accidents), about the quality of the materials or components supplied by the client or about the services of other companies, he must inform the client immediately, if possible before the start of the work communicate work in writing; However, the client remains responsible for his information, orders or deliveries.
4. Unless otherwise agreed, the client must provide the contractor free of charge for use or shared use:
a) the necessary warehouses and workstations on the construction site,
b) existing access roads and sidings,
c) existing connections for water and energy.
The contractor bears the costs for consumption and the knife or meter, several
Contractors bear this proportionately.
5. The contractor must protect the services he has carried out and the items handed over to him for execution against damage and theft until acceptance. At the client's request, he must protect them from winter damage and groundwater and also remove snow and ice. If the obligation according to sentence 2 is not already incumbent on him according to the contract, the remuneration is regulated according to Section 2 No. 6.
6. Substances or components that do not correspond to the contract or the samples must be removed from the construction site at the order of the client within a period specified by the client. If this does not happen, they can be removed at the contractor's expense or sold for his account. 7. Services that are identified as defective or in breach of contract during execution must be replaced by the contractor at his own expense with ones that are free of defects. If the contractor is responsible for the defect or non-conformity, he must also compensate for the resulting damage. If the contractor does not fulfill his obligation to remedy the defect, the client can set him a reasonable deadline to remedy the defect and declare that he will withdraw the order if the deadline has expired without result (Section 8 No. 3).
8. (1) The contractor must carry out the service in his own company. With the written consent of the client, he may transfer them to subcontractors. Consent is not necessary for services for which the contractor's business is not equipped. If the contractor does not provide services in his own company without the written consent of the client,
Although his business is set up for this, the client can set a reasonable deadline for him to begin the service in his own business and declare that he will withdraw the order if the deadline has expired without result (Section 8 No. 3).
(2) When subcontracting construction work to subcontractors, the contractor must apply the procurement and contract regulations for construction work.
(3) The contractor must inform the client of the subcontractors upon request.
9. If objects of antiquity, art or scientific value are discovered on a property when carrying out the service, the contractor must report the find to the client before any further discovery or modification and deliver the objects to him according to further instructions. The reimbursement of any additional costs is governed by Section 2 No. 6. The client has the rights of the discoverer (Section 984 BGB).
10. The condition of parts of the service must be determined jointly by the client and contractor upon request if these parts of the service are withdrawn through further execution of the test and determination. The result must be recorded in writing.
§ 5 Execution deadlines
1 . The execution must begin, be adequately promoted and completed after the binding deadlines (contractual deadlines). Individual deadlines contained in a construction schedule are only considered contractual deadlines if this is expressly agreed in the contract.
2. If no deadline has been agreed for the start of execution, the client must provide the contractor with information about the expected start upon request. The contractor must begin within 12 working days of the request. The client must be notified of the start of execution.
3. If workers, equipment, scaffolding, materials or components are so inadequate that the execution deadlines obviously cannot be met, the contractor must immediately remedy the situation upon request.
4. If the contractor delays the start of execution, falls behind with completion, or does not comply with the obligation mentioned in number 3, the client can demand compensation in accordance with Section 6 No. 6 or pay the contractor one if the contract is maintained set a reasonable deadline for the fulfillment of the contract and declare that he will withdraw the order if the deadline has expired without result (Section 8 No. 3).
§ 6 Hindrance and interruption of execution
1. If the contractor believes that the proper execution of the service is being hindered, he must immediately notify the client in writing. If he fails to report, he is only entitled to have the hindering circumstances taken into account if the client was obviously aware of the fact and its hindering effect.
2. (1) Execution deadlines are extended if the hindrance is caused by:
a) due to a circumstance from the client's risk area,
b) through a strike or a lockout ordered by the employers' professional representatives
operation of the contractor or in a company working directly for him,
c) due to force majeure or other circumstances that are unavoidable for the contractor.
(2) Weather influences during the execution period, which would normally have to be expected when the offer was submitted, are not considered a hindrance.
3. The contractor must do everything that can reasonably be expected of him to enable the work to continue. As soon as the hindering circumstances no longer apply, he must immediately and immediately resume work and notify the client of this.
4. The extension of the deadline is calculated based on the duration of the disability with a surcharge for the resumption of work and any postponement to a less favorable time of year.
5. If the execution is likely to be interrupted for a longer period of time without the service becoming permanently impossible, the services carried out must be invoiced according to the contract prices and the costs that have already been incurred by the contractor must also be reimbursed in the contract prices for the part of the service that has not been carried out are included.
6. If the hindering circumstances are the responsibility of one party to the contract, the other party is entitled to compensation for the demonstrably incurred damage and lost profits, but only in the event of intent or gross negligence.
7. If an interruption lasts longer than 3 months, either party can terminate the contract in writing after this period has expired. Billing is governed by numbers 5 and 6; If the contractor is not responsible for the interruption, the costs of clearing the construction site must also be reimbursed, provided they are not included in the remuneration for the services already carried out.
§ 7 Distribution of risk
1 . If the service carried out in whole or in part is damaged or destroyed before acceptance due to force majeure, war, riots or other objectively unavoidable circumstances for which the contractor is not responsible, the contractor has the claims for the parts of the service carried out in accordance with § 6 No. 5; There is no mutual obligation to pay compensation for other damages.
2. The service carried out in whole or in part includes all services directly related to the structure and incorporated into its substance, regardless of their degree of completion.
3. The service carried out in whole or in part does not include the materials and components that have not yet been installed as well as the construction site equipment and stakeouts. The service carried out in whole or in part also does not include construction aids, e.g. B. Scaffolding, even if these are awarded as a special service or independently.
§ 8 Termination by the client
1 . (1) The client can terminate the contract at any time until the service has been completed.
(2) The contractor is entitled to the agreed remuneration. However, he must take credit for
what he saves on costs as a result of the cancellation of the contract or acquires or maliciously fails to acquire through other use of his labor and his business (§ 649 BGB).
2. (1) The client can terminate the contract if the contractor stops making payments or applies for insolvency proceedings or a comparable legal procedure or if such proceedings are opened or the opening of which is rejected due to insufficient assets.
(2) The services carried out must be invoiced in accordance with Section 6 No. 5. The client can demand compensation for non-fulfillment of the remainder.
3. (1) The client can terminate the contract if, in the cases of Section 4 No. 7 and 8 Paragraph 1 and Section 5 No. 4, the set deadline has expired without result (withdrawal of the order). The withdrawal of the order can be limited to a self-contained part of the contractual service.
(2) After the order has been withdrawn, the client is entitled to have the unfinished part of the service carried out by a third party at the contractor's expense, but his claims for compensation for any further damage that may arise remain. He is also entitled to forego further execution and to demand compensation for non-performance if the execution is no longer of interest to him for the reasons that led to the withdrawal of the order.
(3) To continue the work, the client can use equipment, scaffolding, other facilities available on the construction site and materials and components delivered against appropriate compensation.
(4) The client must send the contractor a list of the additional costs incurred and his other claims no later than 12 working days after settlement with the third party.
4. The client can withdraw the order if the contractor made an agreement on the occasion of the award that constitutes an inadmissible restriction of competition. Termination must be given within 12 working days of the reason for termination becoming known. Number 3 applies accordingly.
5. Termination must be declared in writing.
6. The contractor can measure and accept the services he has carried out as soon as possible
demand termination; He must immediately submit a verifiable invoice for the services carried out.
7. A time-based contractual penalty forfeited due to delay can only be claimed for the period up to the day of termination of the contract.
§ 9 Termination by the contractor
1. The contractor can terminate the contract:
a) if the client fails to perform an action incumbent on him and thereby the contractor
is unable to carry out the service (default of acceptance according to §§ 293 ff. BGB),
b) if the client does not make a due payment or is otherwise in default.
2. Termination must be declared in writing. It is only permissible if the contractor has unsuccessfully set a reasonable deadline for the client to fulfill the contract and has declared that he will terminate the contract if the deadline has expired without result.
3. The previous services must be invoiced according to the contract prices. In addition, the contractor is entitled to appropriate compensation in accordance with Section 642 of the German Civil Code (BGB); Any further claims of the contractor remain unaffected.
§ 10 Liability of the contracting parties
1 . The contracting parties are liable to each other for their own negligence as well as for the negligence of their legal representatives and the persons they use to fulfill their obligations (§§ 276, 278 BGB).
2. (1) If a third party suffers damage in connection with the service for which both contracting parties are liable due to statutory liability provisions, the general legal provisions apply to the compensation between the contracting parties, unless otherwise agreed in the individual case. If the third party's damage is only the result of a measure ordered by the client in this form, he will bear the damage alone if the contractor has informed him of the danger associated with the ordered execution in accordance with Section 4 No. 3.
(2) The contractor bears the damage alone to the extent that he has covered it through insurance under his statutory liability or could have covered it through insurance at premiums and premium surcharges in accordance with the tariff, which are not based on exceptional circumstances, with an insurer licensed to do business in Germany.
3. If the contractor is obliged to pay damages to a third party in accordance with Sections 823 ff. of the German Civil Code (BGB) due to unauthorized entry into or damage to adjacent properties, due to the removal or storage of soil or other objects outside the areas instructed by the client or due to the consequences of unauthorized blocking of paths or watercourses, he alone bears the damage in relation to the client.
4. In the relationship between the contracting parties, the contractor alone is liable for the violation of industrial property rights if he himself offered the protected process or the use of protected objects or if the client prescribed the use and pointed out the property right.
5. If one contracting party is exempt from the obligation to compensate the other in accordance with numbers 2, 3 or 4, this exemption also applies to its legal representatives and vicarious agents if they have not acted intentionally or with gross negligence.
6. If a contracting party is claimed by the third party for damage that the other contracting party has to bear according to numbers 2, 3 or 4, it can demand that its contracting party release it from the liability towards the third party. It may not recognize or satisfy the third party's claim without first giving the other contracting party the opportunity to express its opinion.
§ 11 Contractual penalty
1. If contractual penalties have been agreed, Sections 339 to 345 of the German Civil Code (BGB) apply.
2. Is the contractual penalty agreed in the event that the contractor does not do so within the stipulated period
fulfilled, it becomes due if the contractor defaults.
3. If the contractual penalty is calculated in days, only working days count. If it is calculated in weeks, each working day of a week or part thereof is counted as 1/4 week.
4. If the client has accepted the service, he can only demand the penalty if he reserved this at the time of acceptance.
§ 12 Acceptance
1 . If the contractor requests acceptance of the service after completion, possibly before the end of the agreed execution period, the client must carry it out within 12 working days; another deadline can be agreed.
2. Upon request, self-contained parts of the service must be specifically inspected.
3. Due to significant defects, acceptance can be refused until they have been eliminated.
4. (1) Formal acceptance must take place if one contracting party requests it. Any party
can call in an expert at their expense. The findings must be recorded in writing in a joint negotiation. Any reservations due to known defects and contractual penalties must be recorded in the minutes, as well as any objections by the contractor. Each party receives a copy.
(2) The formal acceptance can take place in the absence of the contractor if the appointment was agreed or the client had invited it with sufficient notice. The result of the acceptance must be communicated to the contractor as soon as possible.
5. (1) If no acceptance is required, the service is deemed to have been accepted 12 working days after written notification of completion of the service.
(2) If no acceptance is required and the client has used the service or part of the service, acceptance is deemed to have taken place after 6 working days after the start of use, unless otherwise agreed. The use of parts of a structure to continue work does not constitute acceptance.
(3) The client must assert reservations due to known defects or contractual penalties no later than the times specified in paragraphs 1 and 2.
6. Upon acceptance, the risk is transferred to the client, unless he already bears it in accordance with Section 7.
§ 13 Claims for defects
1. The contractor must provide the client with his service free of material defects at the time of acceptance. The service is free of material defects at the time of acceptance if it has the agreed quality and complies with the recognized rules of technology. If the quality is not agreed, the service is free of material defects at the time of acceptance,
a) if they are in accordance with the contract, otherwise
b) suitable for normal use and has a quality that is common for works of the same type and that the client can expect based on the type of service.
2. In the case of services based on samples, the properties of the sample are deemed to be the agreed quality, unless deviations are viewed as meaningless according to common practice. This also applies to samples that are only recognized as such after the contract has been concluded.
3. If a defect can be traced back to the service description or to orders from the client, to the materials or components supplied or prescribed by the client, or to the quality of the advance work of another entrepreneur, the contractor is liable unless he has provided him with the information in accordance with Section 4 No . 3 obligatory notification made.
4. (1) If no limitation period has been agreed in the contract for claims for defects, it is 4 years for buildings and 2 years for work on property and for parts of combustion systems touched by fire. Deviating from sentence 1, the limitation period for fire-contact and exhaust gas-insulating parts of industrial combustion systems is 1 year.
(2) In the case of mechanical and electrical/electronic systems or parts thereof where maintenance has an impact on safety and functionality, the limitation period for claims for defects is, in deviation from paragraph 1, 2 years if the client has decided to charge the contractor for maintenance not to be transferred for the duration of the limitation period.
(3) The period begins with acceptance of the entire service; It only begins with partial acceptance for self-contained parts of the service (§ 12 No. 2).
5. (1) The contractor is obliged to remedy all defects that arise during the limitation period and that are attributable to performance in breach of contract at his own expense if the client requests this in writing before the deadline expires. The claim to have the reported defects rectified expires after 2 years, starting from receipt of the written request, but not before the expiry of the standard deadlines according to number 4 or the deadline agreed in their place.
After acceptance of the defect elimination service, a limitation period of 2 years begins again for this service, which, however, does not end before the expiry of the standard deadlines according to number 4 or the deadline agreed in its place.
(2) If the contractor does not comply with the request to remedy the defects within a reasonable period of time set by the client, the client can have the defects remedied at the contractor's expense.
6. If the elimination of the defect is unreasonable for the client or is impossible or would require a disproportionate amount of effort and is therefore refused by the contractor, the client can reduce the remuneration by making a declaration to the contractor (§ 638 BGB).
7. (1) The contractor is liable for damages resulting from injury to life, body or health in the event of culpably caused defects.
(2) In the event of defects caused intentionally or through gross negligence, he is liable for all damages.
(3) In addition, the client must be compensated for any damage to the structure for the production, maintenance or modification of which the service is used if there is a significant defect that significantly impairs its usability and is due to the contractor's fault. The contractor only has to compensate for any damage that goes beyond this if
a) if the defect is due to a violation of the recognized rules of technology,
b) if the defect consists in the absence of a contractually agreed quality or c) if the contractor covers the damage by insuring his legal liability
has covered or could have covered such insurance at tariff premiums and premium surcharges not based on exceptional circumstances with an insurer licensed to do business in Germany.
(4) Deviating from number 4, the statutory limitation periods apply if the contractor has or could have protected himself through insurance in accordance with paragraph 3 or if special insurance cover has been agreed.
(5) A limitation or extension of liability can be agreed in justified special cases.
§ 14 Billing
1. The contractor must invoice his services in a verifiable manner. He must prepare the invoices clearly, adhering to the order of the items and using the designations contained in the contract components. The quantity calculations, drawings and other documents required to prove the type and scope of the service must be enclosed. Changes and additions to the contract must be specifically identified in the invoice; they must be invoiced separately upon request.
2. The determinations necessary for billing must be made together, if possible, as the service progresses. The billing provisions in the technical contractual conditions and the other contractual documents must be observed. For services that are difficult to determine if work continues, the contractor must request joint determinations in a timely manner.
3. For services with a contractual execution period of no more than 3 months, the final invoice must be submitted no later than 12 working days after completion, unless otherwise agreed; This deadline is extended by 6 working days for every additional 3 months of execution period.
4. If the contractor does not submit a verifiable invoice even though the client has given him a reasonable deadline to do so, the client can prepare it himself at the contractor's expense.
§ 15 Hourly wage work
1. (1) Hourly wage work is billed according to the contractual agreements.
(2) If no agreements have been made regarding the remuneration, the usual local remuneration applies
Compensation. If this cannot be determined, the contractor's expenses for wage and salary costs on the construction site, wage and salary costs on the construction site, material costs on the construction site, costs of the facilities, equipment, machines and mechanical systems on the construction site, freight, transport and loading costs, social security contributions and Special costs that arise from economical business management
with appropriate surcharges for overhead costs and profit (including general entrepreneurial risk) plus VAT.
2. If the client requires that the hourly wage work be supervised by a foreman or another supervisor, or is the supervision in accordance with
relevant accident prevention regulations are necessary, number 1 applies accordingly.
3. The client must be notified of the execution of hourly wage work before it begins. About the hours worked and the hours required, especially
The expenses to be reimbursed for the consumption of materials, for the provision of facilities, devices, machines and mechanical systems, for freight, transport and loading services as well as any special costs are, unless otherwise agreed, lists (hourly wage sheets) on a working day or a week, depending on the traffic customs. to submit. The client must return the hourly wage slips certified by him immediately, but at the latest within 6 working days of receipt. He can raise objections on the hourly wage slips or separately in writing. Hourly wage slips that are not returned on time are considered accepted.
4. Hourly wage invoices must be submitted as soon as the hourly wage work has been completed, but at least every 4 weeks. Section 16 applies to payment.
5. If hourly wage work was agreed, but there were doubts about the scope of the hourly wage payments due to the hourly wage slips not being submitted on time
exist, the client can demand that a remuneration be agreed for the demonstrably carried out services, which in accordance with number 1 paragraph 2 for an economically justifiable amount of working time and consumption of materials, for the provision of facilities, devices, machines and mechanical equipment Facilities, freight, transport and loading services as well as any special costs are determined.
§ 16 Payment
1 . (1) Advance payments must be made upon request in the amount of the value of the proven contractual services, including the stated VAT amount applicable thereto, at the shortest possible intervals. The services must be proven by a verifiable list, which must enable a quick and reliable assessment of the services. Services that are specifically manufactured and provided for the required service are also considered to be services
Components as well as the materials and components delivered to the construction site if, at his discretion, ownership of them is transferred to the client or appropriate security is provided.
(2) Counterclaims can be retained. Other retentions are permitted only in the cases provided for in the contract and legal provisions.
(3) Claims for advance payments are due within 18 working days of receipt of the statement.
(4) The advance payments have no influence on the liability of the contractor; they do not count as acceptance of parts of the service.
2. (1) Advance payments can also be agreed after the contract has been concluded; Sufficient security must be provided for this upon request by the client.
Unless otherwise agreed, these advance payments are subject to interest at 3% above the base interest rate in Section 247 of the German Civil Code (BGB).
(2) Advance payments are to be offset against the next due payments to the extent that they are to be used to compensate for services for which the advance payments were granted.
3. (1) The claim to the final payment is due immediately after checking and confirming the final invoice submitted by the contractor, at the latest within 2 months of receipt. The review of the final invoice should be accelerated if possible. If it is delayed, the undisputed balance must be paid immediately as an advance payment.
(2) The unconditional acceptance of the final payment excludes additional claims if the contractor has been informed of the final payment in writing and the exclusion effect has been pointed out.
(3) It is equivalent to a final payment if the client finally and in writing refuses further payments, citing payments made.
(4) Claims made previously but not settled will also be excluded if they are not reserved again.
(5) A reservation must be declared within 24 working days of receipt of the notification in accordance with paragraphs 2 and 3 about the final payment. It will become invalid if a verifiable invoice for the reserved claims is not submitted within a further 24 working days or, if this is not possible, the reservation is justified in detail.
(6) The exclusion periods do not apply to a request for correction of the final invoice and payment due to measurement, calculation and transmission errors.
4. Self-contained parts of the service can be finally determined and paid for after partial acceptance without regard to the completion of the remaining services.
5. (1) All payments must be accelerated as much as possible.
(2) Discounts that have not been agreed upon are not permitted.
(3) If the client does not pay when due, the contractor can set a reasonable grace period. If he does not pay within the grace period, the contractor is entitled to interest from the end of the grace period in the amount of the interest rates specified in Section 288 of the German Civil Code (BGB), unless he suffers higher damages as a result of the default
proven.
(4) If the client does not pay the undisputed balance due within 2 months of receipt of the final invoice, the contractor is entitled to interest on this balance from this point onwards, in deviation from paragraph 3 (without setting a grace period), in the amount of the interest rates specified in Section 288 of the German Civil Code (BGB). , if
he does not provide evidence of higher damage caused by the delay.
(5) In the cases of paragraphs 3 and 4, the contractor may stop work until payment is made, provided that a reasonable grace period previously set for the client has expired without success.
6. The client is entitled to make payments to the contractor's creditors in order to fulfill his obligations under numbers 1 to 5, insofar as they are involved in the execution of the contractor's contractual service on the basis of a service or work contract concluded with him, due to default in payment by the contractor rightly refuse to continue their service and the direct payment is intended to ensure the continuation of the service. At the request of the client, the contractor is obliged to declare within a deadline set by the client whether and to what extent he recognizes the claims of his creditors; If this declaration is not submitted on time, the requirements for direct payment are deemed to have been accepted.
§ 17 Security deposit
1 . (1) If security is agreed, Sections 232 to 240 of the German Civil Code (BGB) apply, unless otherwise stated in the following provisions.
(2) The security serves to ensure the contractual execution of the service and the claims for defects.
2. Unless otherwise agreed in the contract, security can be provided by retaining or depositing money or by guaranteeing a credit institution or credit insurer, provided that the credit institution or credit insurer
in the European Community or in a state party to the Agreement on the European Economic Area or in a state party to the WTO Agreement on Government Procurement.
3. The contractor has the choice between different types of security; he can replace one security with another.
4. When providing security through a surety, the prerequisite is that the client has recognized the guarantor as suitable. The guarantee declaration must be made in writing, waiving the objection of advance action (§ 771 BGB); it may not be limited to a specific time and must be issued in accordance with the instructions of the client. The client cannot demand a guarantee as security that obliges the guarantor to pay upon first request.
5. If security is provided by depositing money, the contractor must deposit the amount into a blocked account at a financial institution to be agreed upon, which both parties can only use jointly. The contractor is entitled to any interest.
6. (1) If, as agreed, the client is to withhold the security in partial amounts from his payments, he may reduce the payment by a maximum of 10% until the agreed security amount is reached. He must inform the contractor of the amount withheld
and deposited into a blocked account at the agreed financial institution within 18 working days of this notification. At the same time, he must arrange for this financial institution to appoint the contractor
of the deposit of the security amount. Number 5 applies accordingly.
(2) For smaller or short-term orders, it is permissible for the client to only pay the retained security amount into a blocked account upon final payment.
(3) If the client does not pay the withheld amount on time, the contractor can set a reasonable grace period for this. If the client allows this to pass, the contractor can demand immediate payment of the withheld amount and then no longer needs to provide security.
(4) Public clients are entitled to take the amount retained as security into their own safekeeping account; the amount does not bear interest.
7. The contractor must provide security within 18 working days of the conclusion of the contract, unless otherwise agreed. As far as he this
If the obligation has not been fulfilled, the client is entitled to withhold an amount equal to the agreed security from the contractor's credit. Otherwise, numbers 5 and 6 apply accordingly, except for paragraph 1, sentence 1.
8. (1) The client must return any unused security for the fulfillment of the contract at the agreed time, at the latest after acceptance and provision of security for claims for defects, unless the client's claims that are not covered by the security provided for claims for defects, have not yet been fulfilled. He may then withhold a corresponding portion of the security for these contractual fulfillment claims.
(2) The client must return any unused security for defect claims after 2 years, unless another return date has been agreed. However, if his asserted claims have not yet been fulfilled at this point in time, he may withhold a corresponding portion of the security.
§ 18 Disputes
1 . If the requirements for a place of jurisdiction agreement in accordance with Section 38 of the Code of Civil Procedure are met, the place of jurisdiction for disputes arising from the contract is based on the location of the office responsible for representing the client in court, unless otherwise agreed. It must be communicated to the contractor upon request.
2. (1) If differences of opinion arise in contracts with authorities, the contractor should first call the office immediately superior to the contracting authority. This should give the contractor the opportunity to discuss the issue verbally and, if possible, inform him in writing within 2 months of the call and point out the legal consequences of sentence 3. The decision is considered recognized if the contractor does not lodge a written objection with the client within 3 months of receipt of the decision and the client has informed him of the exclusion period.
(2) Upon receipt of the written application to carry out a procedure in accordance with paragraph 1, the statute of limitations for the claim asserted in this application is suspended. If the client or contractor does not wish to continue with the procedure, they should inform the other party of this in writing. The suspension ends 3 months after receipt of the written notice or notification in accordance with sentence 2.
3. In the event of disagreements about the properties of substances and components for which generally applicable testing procedures exist and about the admissibility or reliability of the machines or testing procedures used in the testing, each contracting party may, after prior notification to the other contracting party, request the material-technical examination to be carried out by a state or have a state-recognized materials testing center carried out; their findings are binding. The underlying party bears the costs.
4. Disputes do not entitle the contractor to stop the work.